Monday, October 8, 2012

Day 6: Two Piers Are Framed


It's Monday, October 8 and the crew is back for their second week of work. They worked on the piers that will hold the south wall. From the looks of the forms, there will be a lot of concrete in those piers.

The piers are critical to the life of the barn. The huge amount of pressure from the bank at the back of the barn has forced the barn forward on the foundation. That's what is causing the lean.

The weather is turning colder. There have been freeze warnings but the days are clear and sunny. It should be a good week for working on an old barn.